REPORT SUBMITTALS
- GENERAL CRITERIA
A.
Report Descriptions
Submittals document
various phases in the identification and cleanup of a contaminated
site. Each submittal should be titled with one of the following
names AND the Division 5 Permit number from which it is generated
(Permit # can be found in the center, first line of your permit).
Reports titled with names not included in the following list
may be returned unread:
-
"Soils
Report" -
A report summarizing the laboratory results for testing
of soil samples taken at a site during Division 5 permitted
work for: Tank Abandonment, or Add To/ Alter work performed
on any part of an Underground Storage Tank (UST) system
-
"Community
Health and Safety Plan" -
A report required by the California Occupational Safety
and Health Administration (CALOSHA) covering all hazardous
conditions and required protective equipment for assessment,
remediation, and inspection at a site
-
"Work
Plan for Site Assessment" -
A plan for work to be completed to determine the vertical
and horizontal extent of contamination at a site and the
physical properties of the earth materials/groundwater
in which it occurs
-
"Site
Assessment Report" -
A report documenting activities from approved Work Plan
for Site Assessment which have been performed to determine
the extent of contamination at a site, and characterize
the subsurface materials
-
"Remedial
Action Plan" -
A plan for work to be completed to achieve the cleanup
of site contamination. This plan must be submitted as
a separate document from the Site Assessment.
-
"Quarterly
Progress/Monitoring Report" -
A report documenting all activities that have taken place
during a three month period (these reports are required
when remedial activities continue for a time period longer
than three months or when groundwater has been encountered)
-
"Remedial
Action/Final Closure Report" -
A report documenting corrective activities which have
been performed to remove the contamination from a site
-
"Additional
Requirements: (INSERT REPORT NAME AND ASSOCIATED PERMIT
NUMBER)" -
A report, frequently a letter, submitted to satisfy deficiencies
or discrepancies identified by the Unit’s review of a
previous submittal (responses must address each question
in the Unit’s review in an item-by-item format)
-
"No
Further Action Letter Request" –
A letter or report requesting "No Further Action"
by LAFD which was not generated by Division 5 permit work
(Will be charged $242 fee for services)
B.
General Requirements
-
The owner
or operator of the UST must notify the Los Angeles Fire
Department within 24 hours of the detection of the unauthorized
release
-
The owner
or operator must take immediate measures to stop the
release and remove any remaining substances from the
UST
-
Names and
addresses All
submittals must clearly identify the names and addresses
of the site, the Responsible Party and the current property
owner(s).
-
The title page
must contain the associated Division 5 Permit Number
-
Two copies
(double sided
whenever possible) of each document must be submitted
if groundwater contamination is suspected. If not, then
only one copy is required.
-
Technical
submittals must contain a wet ink signature and seal
by one of the following California licensed professionals:
-
Registered
Geologist (RG)
-
Certified
Engineering Geologist (CEG)
-
Registered
Civil Engineer (RCE)
-
Registered
Geotechnical Engineer (GE)
-
All work
must be performed under the responsible charge of an RG,
CEG, RCE, or GE. A
statement is required in the report indicating that the
licensed professional in responsible charge supervised
or personally conducted all work associated with the project
within the purview of the professional as defined in the
Professional Engineers Act or the Registered Geologists
Act of the California Code of Regulations
-
Reports shall
contain conclusions and recommendations based
on the submitted data and documented analyses (clearly
state any assumptions and interpretations made to analyze
the data)
-
Critical
figures and tables must
be submitted in each report to justify the conclusions
and recommendations, if any, set forth in the report
-
Workplans
must be approved by the Unit prior
to conducting the work, unless a response is not received
from the Unit within 60 days of submittal
-
The Unit
must be notified 72 hours prior
to commencing any significant investigation, assessment,
or remediation activities on-site (all attempts should
be made to notify the Unit with respect to last minute
changes)
-
A Community
Health and Safety Plan must be submitted prior to
conducting any field work and must be available at the
site
-
Deviations from
these Guidelines may be acceptable provided the alternative
procedures are approved by the Unit as being equivalent
to the standard provisions of the Guidelines
C.
Streamlining the Submittal
Process
In accordance
with United States Environmental Protection Agency (EPA)
directives to streamline the regulatory review (oversight)
process, the following changes in the report submitting
procedures have been adopted by the Unit effective with
the issuance of the current Guidelines:
-
Submit an
electronic copy of reports, with
the printed copy, on compact disc (CD). The format must
be in Adobe Acrobat (.pdf).
-
Upon notification,
a Work Plan for Site Assessment which completely
defines the extent of contamination must be submitted.
-
Upon completion
of site assessment, a Site Assessment Report shall
be submitted, and if needed, a separate Remedial Action
Plan.
-
The Remedial
Action Plan must describe in detail the proposed
cleanup method.
-
Upon completion
of site remediation, a Remedial Action/Final Closure
Report must be submitted.
-
Unless directed
otherwise by the Project Inspector/Engineer, Quarterly
Progress / Monitoring reports are required when site
assessment or remedial activities take longer than three
months or groundwater is encountered.
-
Protocol and
procedures for all work must be specified and follow the
report descriptions and requirements in these guidelines.
D.
Mailing Address
All correspondence
should be submitted to the following address:
Los Angeles Fire
Department, UST Unit
221 N. Figueroa St., Suite 1500, Los Angeles, CA 90012
Correspondence should
also include the Project Inspector/Engineer’s name if it is
known. Information submitted by facsimile (FAX) must be followed
up with printed documents as soon as possible.
Rev. 05-29-03
|